In a typical five-day period, the planning department programs a particular machine to work for 80 hours – its loading time. Changeovers and set-ups take an average of 4 hours and breakdown failures average 3 hours every five days. The time when the machine cannot work because it is waiting for material to be delivered from other parts of the process is 2 hour on average and during the period when the machine is running, it averages 98 per cent of its rated speed. Subsequently 4 per cent of the parts processed by the machine are found to be defective in some way. Based on the information given above, calculate the Overall Equipment Effectiveness.
a) 83.5096
b) 95.10%
c) 89.6096
d) 92.44% Leave blank