For an organization, the following project schedule is given. Assume that all times are in days.

Task
Predecessor
Normal Time
Crash Time
Crash Cost Slope
A
None
7
7
NA
B
A
3
3
NA
C
A
8
4
600
D
A
4
4
NA
E
B
6
5
600
F
C, D
2
2
NA
G
E, F
6
6
NA
H
F
5
3
400
I
G, H
4
4
NA
J
I
2
2
NA

In a 3- to 4-page Microsoft Word document, address the following:

  • Draw the AON project network using Microsoft Project, Microsoft Visio, or some other tool capable of creating such a network. Perform a critical path analysis for the network and calculate the ES, EF, LS, and LF times.
  • Calculate the slack time for each activity.
  • Identify the critical path.
  • Assume that the organization will receive a $400 bonus for each day the duration of the project is shortened. The organization is also responsible for paying the crash cost associated with shortening the schedule. To maximize the net profit, identify which task you should crash and by how much.

Support your responses with examples.

Cite any sources in APA format.

 
"Looking for a Similar Assignment? Get Expert Help at an Amazing Discount!"
Looking for a Similar Assignment? Our Experts can help. Use the coupon code SAVE30 to get your first order at 30% off!

Hi there! Click one of our representatives below and we will get back to you as soon as possible.

Chat with us on WhatsApp