Product Development. Consider the simplified set of activities in the Table below for the development of a consumer product from initiation through the market test phase.

Table is attached in the attachments.

  1. Draw the AOA network for this project (no forward or backward passes are required).
  2. Calculate total slacks and free slacks, and interpret their meanings.
  3. Determine the critical path and interpret its meaning.
 