This question will help you better understand the capacity of the “Mixing station. Every two minutes the operator at the “Mixing” station receives a mixing bowl from the “Batching” station containing 13 pounds of ingredients ready to mix. Each doughnut requires 2 ounces of ingredients. It takes the mixing operator 3 minutes to place all of the bowl onto the mixer and mix the ingredients into dough. There are 3 mixers at the “Mixing” station. What is the daily doughnut capacity of the “Mixing” station assuming one operator works one eight hour shift? Enter your answer as a number only such as “1456” if you calculate that the station’s capacity as 1,456 doughnuts per day.
 