USE THE MRP TABLE INCLUDED WITH THE QUIZ FOR THIS PROBLEM. The MPS calls for 80 units of Product W in week 5. Each W requires 2 of Part X and 3 of Part Y. Each Y requires 3 of Part Z. Current projected on-hand includes: 30 of Part X, 20 of Part Y, and 100 of Part Z. There is a scheduled receipt of 20 Y s in week 2. All items have a 1 week lead time and are ordered LFL. The Planned Order releases for Parts X and Z are Group of answer choices 160 units of X in week 3 and 330 units of Z in week 2. 160 units of X in week 3 and 720 units of Z in week 2. 130 units of X in week 3 and 560 units of Z in week 2. 130 units of X in week 3 and 500 units of Z in week 2. 130 units of X in week 2 and 560 units of Z in week 1.?
 