Unit 6 Project Management
Using the information provided in the Gantt chart below, construct the project activity network using the activity-on-node (AON) methodology, and label each node. Identify the critical path and other paths through the network.
Activity | Duration | Predecessors | |||
A | 3 | — | |||
B | 5 | A | |||
C | 7 | A | |||
D | 3 | B, C | |||
E | 5 | B | |||
F | 4 | D | |||
G | 2 | C | |||
H | 5 | E, F, G |